Description
The Union & Mont Albert Rd Level Crossing Removal Project is located on the Belgrave / Lilydale rail line, approximately 12 km east of the Melbourne CBD. The project boundary is located within the City of Booroondara and the Whitehorse City Council municipalities in the suburbs of Surrey Hills and Mont Albert. The level crossings were removed and replaced with a ‘Rail Under Road’ solution which features a lowered rail line crossing beneath the two roads in a cutting. Two existing stations were removed and replaced with a new single consolidated station constructed between the two existing stations servicing both communities.
Rating Highlights
Category |
Credits |
Achievements/Risks |
Energy and Carbon |
Ene-1 |
The Project achieved a verified level of 3 with a score of 13.48.
- Successfully reduced its energy consumption by 12,082 tonnes of CO2 emissions compared to the base case.
- Major construction phase savings were due to using Green Power and offsetting site office emissions.
- Utilised renewable B5 biodiesel for all SEPA-supplied fuel.
- Avoided vegetation loss through efficient design and purchased native vegetation offsets.
- Installed multimodal PIDs using solar electricity.
- Adopted a consolidated station design, avoiding the need for a second set of full-sized standard station platforms and associated permanent external lighting.
- Incorporated a 70-kW solar array for station operation.
- Included energy-efficient measures such as evaporative cooling, optimised internal and external lighting layouts, and a thermally efficient building envelope.
- Reduced plant and equipment fuel burn through value engineering.
- Achieved a remarkable 61% reduction in carbon emissions compared to the Base Case footprint.
Overall, the Project demonstrated commitment to sustainability through effective implementation of various initiatives.
|
Heritage |
Her-1 |
The Project achieved a verified level of 3 with a score of 4.99.
- Undertook thorough assessments and consultations to integrate community heritage values into studies and designs.
- Collaborated with Aboriginal Victoria and traditional owner groups to identify 10 historic heritage sites and 4 significant trees.
- Promoted local history by repurposing and relocating the historical Mont Albert Station to a new heritage deck area for community use.
- Enhanced the heritage deck area with furniture detailing that reflects the heritage rail character, and used contextually relevant materials such as timber, brick and bluestone.
- Salvaged and reused heritage features, including the heritage palm tree.
- Implemented a planting strategy to preserve and enhance local heritage.
- Took measures during construction to minimize adverse impacts on heritage sites, including project-specific training and vibration monitoring.
- Enhanced heritage values through archaeological digs and restoration of the historic Mont Albert Station building.
The Project Exhibited a thorough and thoughtful approach to preserving and celebrating local heritage throughout the project's development and implementation. |
Materials |
Mat-1 |
The Project achieved a verified level of 3 with a score of 5.99.
- GHG Reduction: Achieved a total reduction of 32% from Base Case to As Built, equivalent to 16,964 tonnes CO2-e.
- EnviroPoints: Achieved a total reduction of 31% from Base Case to As Built, amounting to 153,546 tonnes CO2-e.
- Piling: Reduced retaining wall cuts, saving 2,519 tonnes CO2-2 (4.9%)
- Tank Slab-Concrete: Narrowed trench and reduced slab thickness, saving 7,609 tonnes CO2-e (14.7%)
- Tank Slab-Reinforcement: Reduced reinforcement, saving 1,464 tonnes CO2-e (2.8%)
- Shotcrete: Reduced retaining wall cuts, saving 112 tonnes CO2-e (0.2%)
- Steel Structure: Fewer platforms, saving 1,376 tonnes CO2-e (2.7%)
- Concrete Structure: Reduced concrete use, saving 251 tonnes CO2-e (0.5%)
|
Verified Innovations
Name |
Verification Date |
|
Innovation Type |
Description & Sustainability Benefits |
EV Truck |
02/05/2024
|
|
Innovation technology or process
Victoria first. |
The Project achieved 1 Innovation point.
- Introduced a first-of-its-kind in Victoria EV truck for construction.
- Hired a single cab flatbed EV Truck for use in the construction phase.
- Installed a dedicated charging point to allow recharging through 100% GreenPower.
- Reduced Scope 1 emissions by 25 tonnes of carbon.
- Improved on-site air quality by avoiding particulate emissions from diesel burn.
- Reduced noise emissions to the community.
- Enhanced energy tracking and reporting.
- Provided economic benefits.
|
Propeller |
02/05/2024
|
|
Innovation technology or process
Piggyback Victoria first.
|
The Project achieved 1 Innovation point.
- Adopted Propeller software for drone data capture throughout the construction phase.
- Reduced carbon footprint compared to traditional surveying methods.
- Allowed access to hazardous or inaccessible areas (e.g., rail corridor).
- Reduced time and labour spent capturing data.
- Supported project planning and the Digital Twin Victoria initiative.
|
iSupply |
02/05/2024 |
|
Innovation challenge
|
Project achieved 0.75 Innovation points.
- Collaboration with Nation Partners
- Contract with Bingo Industries waste management and recycling
- Usage of Site Hive (Hexanode and Software): Environmental monitoring.
|
Guard Dog |
02/05/2024
|
|
Innovation technology or process
Piggyback Australian first |
The Project achieved 3 Innovation points.
- Implemented 12 GuardDogs stormwater drain filters for stormwater management across the site, capable of absorbing 144 litres of hydrocarbons at any one time.
- Filters sediment almost twice as fine as traditional silt socks.
- Made from 100% recycled waste, equivalent to over 11 m² of recycled materials upcycled into the 12 filters.
- Features a heavy-duty design that withstands vehicle traffic.
- Reusable for multiple projects, enhancing sustainability.
- Provides rapid installation due to its adaptable shape.
- Improves water quality by filtering sediment and hydrocarbons.
|
Mental Health Initiative (Energy Project) |
02/05/2024
|
|
Innovation technology or process
Piggyback Australian first |
The Project achieved 3 Innovation points.
- Collaborated with FMSSA for trial design.
- Utilized wearable tech, sleep education, and coaching.
- Based on Mordialloc Freeway project framework.
- Trial demonstrated that monitoring sleep data, combined with education and coaching, resulted in longer objective sleep durations and a trend towards improved subjective sleep quality.
- Implemented a Sleep Study to enhance mental health.
- Benefits included increased energy and performance, improved work-life balance and wellbeing, and increased productivity.
- Reduced project risk linked to fatigue.
|
Certification Date: