This project by Level Crossing Removal Authority has registered for an As Built v1.2 IS Rating.
Overview
The Reservoir level crossing at High Street will be removed and replaced with a rail over road solution including approximately 800 metres of twin elevated structures. The existing Reservoir Station will be demolished and replaced with a new premium station featuring station buildings at ground level and an elevated island platform accessed by stairs and lifts.
Details
- Rating Type Rail
- Registered Date October 2019
- Practical Completion June 2020
- Jurisdiction Australia
- States VIC
- Suburb Reservoir
- Assessor Rachael Lee
Website
To find out more information about this project, visit Level Crossing Removal Project Website: https://levelcrossings.vic.gov.au/projects/high-street-reservoir