EnergyConnect - Design - ISCouncil

EnergyConnect – Design

Project Details

  • Project Owner: Transgrid
  • Rating Type: Design
  • Location: NSW
  • Rating Level: Leading
  • Rating Score: 77.96 (78)
  • IS Project manager: Ben Wade
  • Stakeholders: AECOM ,SecureEnergy Joint Venture (Clough and Elecnor),GHD, Mott MacDonald

Description:

EnergyConnect is a joint project between the Transmission Network Service Providers for New South Wales (Transgrid) and South Australia (ElectraNet) to join their state power grids via a new 330kV above ground transmission line interconnector between Robertstown SA and Wagga Wagga NSW substations, a total distance of approximately 900km and 800MW transfer capacity. The NSW section of the EnergyConnect is registered for IS v1.2 Design and As-built ratings and consists of approximately 700km of new transmission line extending from Wagga Wagga NSW to the South Australian Border.  

EnergyConnect NSW includes: 

  • The construction of two new 330kV transmission lines and one new 500kV transmission line. 
  • A rebuild of an existing 220kV transmission line. 
  • An expansion and upgrade of the existing Buronga substation  
  • A new substation known as Dinawan, located between Jerilderie and Coleambally. 
  • An expansion of the existing Wagga Wagga substation. 

EnergyConnect, once completed, will be Australia’s largest interconnector in the Australian National Electricity Market (NEM). 

Rating Highlights 

Category  Credits  Achievements/Risks 
Water   Wat-1  The Project achieved a verified level of 3 with a score of 6.26. 

The Project achieved a 31% reduction in construction water compared to the base case (1,702ML to 1,172ML). The two main water reduction strategies implemented include use of a non-water-based dust suppression alternative and use of grey water for worker accommodation camps.  

Ecology  Eco-1  The Project achieved a verified level of 3 with a score of 19.47. 

The Project recorded a total of 7 threatened ecological communities, 14 threatened flora species and 7 threatened fauna species present across the project area. To avoid impacts to the high biodiversity and culturally sensitive sites, the following initiatives were implemented: 

  • Relocation of transmission line structures to avoid sensitive areas  
  • Installing at least 1,500 nestboxes to provide fauna habitat for local species  
  • Installing bird diverters on powerlines  
Legacy   Leg-1  The Project achieved a verified level of 3 with a score of 4.63.  

The Project address two priority issues and initiatives for the local communities along the project alignment: local employment, training and education and ecological habitat. In response to the first priority issue, the Project implemented a multi-million-dollar Legacy 100 program to train Australia’s own transmission line construction workforce and a $2 million scholarship fund for engineering students at Charles Strut University.  

 

Verified Innovations 

Name   Verification Date  Project Publication sign off  Innovation Type   Description & Sustainability Benefits 
Guyed Towers  30/01/2024    Innovative Technology or Process  

State First 

The Project received 1 point for this innovation.  

The Project has claimed a NSW first for constructing a transmission line that utilises 330 kV guyed steel lattice structures (or guyed towers). The guyed towers are structures with a central steel column supported by four high-tensile steel cables (guy wires), each 35 mm thick. The guy wires are anchored to the ground providing the structure strength and stability. The sustainability benefits from this innovation include: 

  • A smaller physical construction footprint on the land  
  • A 15% reduction in steel and 25% reducing in concrete used compared to self-supporting conventional towers  
  • Less visually intrusive design  
  • More efficient and safer construction and maintenance requirements  
V2.1 Lan-4  30/01/2024    Innovation Challenge (IC-9)  The Project received 0.5 points for piloting the v2.1 Lan-4 credit and providing feedback to ISC.  
V2.1 Eco-1  30/01/2024    Innovation Challenge (IC-1)  The Project received 1 point for undertaking and addressing Levels 1,2, and 3 of v2.1 Eco-1.  
V2.1 Leg-1  30/01/2024    Innovation Challenge (IC-1)  The Project received 0.25 points for undertaking and addressing Levels 1,2, and 3 of v2.1 Leg-1.  

[embed]https://www.youtube.com/watch?v=x5tYhEMeTiA[/embed]

Stay up to date!

Stay up to date with our latest publications and news.